Running on the sun.

The mega solar array has been active for over a month now and I am pleased to report that the everything has been working very well. I designed the barn foundation as a high mass sand bed storage system, capable of receiving the heat from the solar collectors during the day, storing it in the concrete slab/underslab sand bed, and slowly releasing the built-up heat to the living space. The benefit is higher efficiency from the solar collectors (since they are operating at much lower temperatures than a conventional system with tank storage) and it eliminates the cost and space required for the large water storage tank. The downside, however, is not being able to store the solar heat for more than a day or two. I was only able to find a few resources on this method (like here and here), but it seemed well suited for extreme climate areas like ours here at the north pole, where we pretty much need 100% of the heat capacity during the winter months and thus there is no reason to try to store it in a water tank.
Here are a few pics of the high mass foundation system during construction, showing the underslab insulation, high mass sand bed, hydronic tubing and finally the concrete floor:
Normally, hydronic tubing would be buried in the sand bed as well as the concrete, but here we only have the upper, slab run of tubing...in hindsight, I should've installed it in both areas. The poured slab. The concrete was polished and stained to be used as the finish flooring.
Unfortunately, I picked the snowiest winter in the last half-century to prove out a solar heating system, so the run time has been less than anticipated! However, when we have sun, the system is producing around 250kBTU per day, which is typically enough energy to heat the guest house this time of year. With multiple sunny days in a row, the high mass of the floor absorbs the heat and slowly releases it back to the living space- so far I have not seen more than a 8 degree change in indoor temperature during sunny periods, and we were able to make it through a cold -30F night without the need for supplemental heat one day last week. Very promising indeed. More later....

Tuesday, February 08, 2011

Disentanglement.

One of my greatest fears is to have a failure in the heating system's PEX tubing, which is inconveniently entombed within the concrete slab of the barn. Having thought about if for a few years now, it just doesn't seem like a good idea to seal off any electrical, plumbing or HVAC systems behind walls or under floors- while it may be aesthetically pleasing to have the nervous system of the house well hidden from sight, this makes it difficult if not impossible to upgrade or repair things that break...and sooner or later everything needs fixing, right? Alternately, the concept of disentanglement keeps these systems separate and accessible, usually in chases, raceways and conduits, to increase the adaptability and longevity of the building. I like it, and kept the idea in mind when installing the HRV system, as well as plumbing and electrical runs going to the upper floor of the barn. With all the utilities in place, it looked like this:

Then I built removable soffits and a chaseway to cover it all, which looks like this:

Admittedly, the wood soffits wound up being quite heavy, but can be removed if necessary without destroying anything.

Wednesday, December 29, 2010

Drain water heat recovery.

Even after installing high-efficiency water heaters, low-flow fixtures, and practicing water-conservation habits, we're still faced with the fact that almost all our expensive hot water goes right down the drain. What a waste! Fortunately, I learned about Drain Water Heat Recovery (DWHR) devices from a friend who has been using this technology for over a decade, and was able to incorporate a DWHR unit into the barn. The drain water heat recovery system is basically a large heat exchanger designed to recover the heat from your shower water before it reaches the sewer system. The units consist of a large 3 inch copper pipe with smaller copper pipes wrapped around the outside. As your hot shower water drains through the 3 inch pipe it warms the pipe exterior. This heat is then transferred to the cold incoming water which is flowing through the smaller tubing wrapped around the drain pipe's exterior. There are no moving parts and nothing that can wear out- a very simple design and quite effective because there is lots of surface area and copper is highly conductive. By replacing a vertical section of your drain plumbing with the DWHR unit, a large percentage of the energy in the outgoing hot water can be used to 'preheat' the incoming cold water. I installed the DWHR pipe in a small vertical chase on the main floor to capture the hot water coming from the upstairs master bathroom before it goes under the slab. Putting the DWHR pipe in the basement would obviously be preferred, but since this is a slab-on-grade structure we don't have a basement- this is the only way I could incorporate the DWHR unit into the floor plan. I installed the GFX S3-60 model, which looks like this: Before testing it out, I insulated all of the drain plumbing between the sink, shower and the DWHR pipe. Before...
...and after. The insulating project is to retain the heat and also for sound abatement, since the bathroom is directly above the dining room. For this I used several layers of foam 'sill seal' material wrapped around the pipes and taped.Here is the vertical transition going into the chaseway:
I noticed most of the water noise was coming from the vertical transitions, so I insulated this area with XPS foam board and copious amounts of spray foam- not pretty, but it really cut down the noise and will contain the heat very well.
The building's incoming cold supply water (from our well water) always passes through the heat exchange unit on its way to the hot water heater, automatically extracting heat from the warm water running down the drain line. When I installed the DWHR plumbing, I added two gauges for monitoring the water temp going in, and coming out of, the heat exchanger: Today, I ran hot water through the shower to see how the DWHR would perform- results look good! With the shower running at 101F, the incoming cold well water was being 'preheated' from an initial 50F temp up to about 72F, capturing 44% of the otherwise down-the-drain heat! The manufacturer claims up to 57% efficiency is possible with this model, but that figure is based on a drain water flow rate of 5gpm- much higher than our low-flow sink and shower will ever provide. I'm guessing that around 40% is to be expected and is still very good. And the best part- the DWHR unit was virtually free- our electrical utility provider offered a $400 rebate for installing this $500 system, so the payback should be less than one year. Even at full price, this appears to be a very wise investment and a great energy conservation project. I'd be curious to hear what results others are having with the DWHR units.

Monday, March 15, 2010

Solar Sundays- Part I

My interest in solar projects has been growing for a few years, and I've been researching solar water heating hoping to someday install our own system here at Green Gate. While the government tax rebates for solar projects sounded attractive, we found they would only cover a small system- basically enough for domestic hot water heating, but not for winter space heating. Purchasing a multi-panel solar thermal system would be cost prohibitive. So once again, I came to realize if you want to get something done, you have to learn to do it yourself! Having spent many a night perusing websites and solar forums all winter, I thought it was time to dive in and actually build something myself. With an enthusiastic 'okay' from my wonderful wife, I decided to start dedicating a day every week towards getting a 'prototype' system online and tested. Here is our first solar collector, inspired by designs on the Build it Solar website (one of my favorite resources for a variety of sustainability projects, by the way). Basically, I started by making a 4X8 'box of 2x6 lumber and a plywood bottom.
Then I added 1.5" of polyiso insulation over the plywood.
Next, I soldered together the copper piping that will carry water through the collector- basically 1/2" 'risers' connected to 3/4" manifolds, with an inlet on one end and outlet in the opposite corner. This copper is the expensive part of the project, but I managed to get a pile of tubing for less than scrap prices off Craigslist about a month ago! The photo shows the copper assembly as I was pressure testing it prior to the next step.
To make the 'fins', I took my leftover aluminum heat transfer plates (these are the ones I was using for the in-wall hydronic system installed in the bedrooms recently) and expanded them to 7/8" dia using a pipe, a simple wooden jig, and several blows from a sledgehammer. Good exercise. The fins were then clamped around the tubing using some special vice grip clamps made by a friend of ours for this project. With the clamps forcing the aluminum fins tightly around the copper, I put in several screws through to the plywood base to hold everything in place. This system seemed to work very well once I got the hang of it. Here's a close-up of the fins installed over the tubing.
Then I gave the assembly a coat of black paint.
and finally cut a piece of twinwall polycarbonate for glazing (this is the same stuff I used for our raised bed garden covers). Other than trim pieces over the glazing, it is basically done...next weekend I'll work on the pump and controls.....

Saturday, March 13, 2010

Zone 3 and the heat is on!

The last area calling for heat is the soon-to-be master bathroom in the upper level of the silo. Before tiling the floor, I installed a serpentine of hydronic tubing over the subfloor- basically 1/2" pex tubing pressed into Thermofin-U heat transfer plates, surrounded by 'sleepers' of 3/4" plywood to keep the floor at a consistent level. Schluter Ditra (the orange colored uncoupling membrane) was mortared over the subfloor assembly, and then our local slate cleftstone was mortared over the Ditra. By nature, this slate is not perfectly flat like manufactured tiles, so there was some resulting variability in the pieces. I did my best to maintain smooth transitions from stone to stone. After setting the stones, I put down the last few planks in the entryway, scribing the final board to fit the curve of the stones. The stones still need to be cleaned, sealed and grouted once the mortar has fully cured, but you get the idea. In the boiler room, I connected the lines for the bedroom and bathroom hydronic loops and installed electronic zone valves so they can be regulated separately from the in-slab heat. I also extended the supply and return branches that will run outside to the solar thermal panels we'll be installing this summer. Everything went back together and I fired the system back up this morning without any leaks. The barn is now fully heated and solar-ready!

Sunday, December 13, 2009

Zone 2- the hydronic wall.

Winter arrived hard and fast, bringing the issue of heat to the forefront. The in-slab hydronic system is working fabulously on the main floor, but the hayloft is usually 5-10 degrees cooler and in need of supplemental heat. Since our future plans call for solar-thermal hydronic heating, I want our system to be able to run at the lowest possible temperatures. That said, I opted for a 'hydronic wall' in the hayloft, instead of underfloor heating that requires somewhat higher fluid temps. To get started, I framed in a partition wall to divide the hayloft into two semi-private bedrooms (we decided not to extend the wall all the way up to keep the architecture of the high arched ceiling visible).
Then I built a "hydronic sandwich" using aluminum heat transfer plates between 'sleepers' of 3/4" foil-faced isocyanurate insulation.
With Lisa's help, we routed 1/2" pex tubing in a serpentine pattern through the wall, across the doorway framing, through the smaller side wall, then back to the starting point...then we repeated it in the second bedroom with a separate run of pex...whew!
Here is a closeup of the assembly:
Finally, ready for drywall, which is screwed into the studs being VERY CAREFUL not to puncture the tubing runs.... The aluminum plates help conduct the heat out of the pex tubing and into the drywall surface. The insulation 'sleepers' act as spacers between the drywall and studs, and help direct the heat out outward to the room. The drywall surface readily conducts the heat and radiates it outward to the room. By using this method rather than the more tradition underfloor hydronic installation, more BTUs can be delivered to the room at lower water temps...and it was a much easier and less expensive method in this case. The obvious downside to this method is the risk of puncturing the tubing with fasteners. I took a lot of pictures of the assembly and documented the pex locations so if we ever need to hang a picture on the wall, I'll know where not to pound a nail!

Thursday, January 15, 2009

Hot water.

Reinventing the wheel is sometimes a good thing- like with tanked hot water heaters. I am not a fan of tankless water heaters (they are either terribly inefficient or prohibitively expensive) and I wanted to have a storage tank so that we could add solar-heated water as a future project. However, traditional tanked water heaters are usually poorly insulated and have a limited lifespan (I hate seeing the pile of hot water heaters at our local landfill). There are some well-built models on the market, but they are crazy expensive. Then I found the HH20 water heater (www.howardharrisbuilders.com) and just installed ours this week. While it looks like the same old tanked water heater, it actually uses a heater exchanger (the finned copper coil) to transfer heat from the tank to the plumbing. Since this design keeps the water in the tank separated from the water you actually use, the tank is not pressurized and (in theory) should never burst or leak. So the unit can be built inexpensively using a plastic tank and 2.5" thick insulated walls- very efficient and very durable.
Once the lid is put on, a single 3500W electric heating element extends down the center of the coil to heat the tank water. We also purchased a heat pump retrofit kit (www.airgenerate.com), which will be installed in the spring so that we can heat the water more efficiently and use the exhaust air for home cooling...more on that later. Since the tank is not pressurized, I can also modify it to accept solar heated water when we get to that phase in the future. We paid $350 for the heater- a little more than buying a conventional tanked electric heater, but a great price for the benefits of this design.

Friday, December 05, 2008

Ventilation.

After bringing in a load of fresh timbers to start the post-and-beam framing, the humidy inside the barn went off the charts. The building is so airtight, there is virtually zero natural air exchange and the moisture coming out of the drying timbers had no means of escape. So I hurried and got the Venmar HRV (which has been sitting in a box for over a year now!) hooked up and running. Here is the unit hanging from the ceiling in the utility closet. I connected some temporary ductwork through the wall, just to get the fresh air into the main area of the barn.
The HRV works by means of a counterflow heat exchanger, which maximizes the transfer of heat from the stale exhaust air to the fresh supply air from outside. With claims of 92% efficiency, it seemed to defy the laws of thermodynamics in my mind, so I was skeptical at first. But it works great! Inside the unit, the outgoing air flows one direction and the incoming air flows the opposite direction, so that the coolest outgoing air just barely warms the cold incoming air, and the warmest outgoing air warms the already-sorta-warm incoming air. By arranging the airflows in this way, the incoming air captures nearly all of the heat from the outgoing air before it leaves the house. Of course, I had to put a thermometer in the fresh air duct to see how well it was doing- On a day when the outside temp was around 10F, and the building was at 58F, the fresh incoming air was being 'preheated' to about 53 degrees. At this rate, the HRV will pay for itself in no time!

Sunday, November 16, 2008

Heat on!

Someday, we will have a central heating system (perhaps solar, geothermal, or a wood pellet boiler) that feeds hot water to the barn, house and any other buildings we have by then. But that 'someday' is a long time from today, and it is getting cold outside. So I bought a electric micro boiler and related plumbing to put together a heating system for our in-floor hydronics. Midway through the assembly process, my workspace looked like this: I clamped all the plumbing components to a board that was screwed to the wall of the utility closet, directly over the stub-outs of the in-floor hydronic tubes. I also added two branch lines to feed the upper floor bedrooms and bathroom this winter. The system was fired up yesterday (surprisingly, leak-free!) and is slowly pumping heat into the cold concrete floor...

Monday, August 04, 2008

More adventures in silo-building.

With all the flat surfaces in the barn covered with drywall, it is on to the more difficult areas. I started on the ground level of the silo, which will be dining room once finished. Because of the sharply curved wall, standard drywall wouldn't make the bend, so I went with two layers of thinner 1/4" drywall. After the entire wall was covered with the first layer, I trowed on a coating of joint compound before screwing the second layer in place. The end result was a standard 1/2" thick wall that formed a nice curve, but it took twice as much time and twice as much money to do it (ironically, 1/4" drywall costs more than 1/2" drywall, and you need twice as much!). I am rethinking how I do the upper level....

My dad came over and helped rig up the scaffolding around the silo exterior so I could prepare it for the stucco. Thanks to Keith borrowing me some of his scaffolding, we were able to circle the entire silo and tie everything together solid. I have been dreading this job all winter, but with the scaffolding so rigid, it is actually pleasant to be working up high now. The original layer of XPS foam was covered with Tyvek Stuccowrap, windows flashed (again), and then covered with 1" EPS foamboard, screwed through both layers and into the studs.

Monday, January 28, 2008

I installed a Quadra Fire wood pellet stove to heat the barn for the winter and to provide supplemental heat once the in-floor system is completed. Having no experience with wood pellet heating, I was skeptically hopeful about how this would work. Conceptually, it seems ideal- sawdust (in this case, a waste product from the wood products manufacturing industry) is formed into pellets by a relatively simple extrusion and drying process, then sold as fuel. It's natural, renewable, locally-produced, and inexpensive- Sustainable, Carbon Neutral heating at its finest! The whole idea still seems too good to be true.... So, after looking at several different pellet burners, we settled on the Quadra-Fire model for a variety of reasons- it had the lowest emmissions, highest efficiency, is American-made, and it has the rustic, aesthetic appeal we wanted in the barn. I set it in place, wired in a programmable thermostat, and installed the exhaust venting and air-intake systems through the wall (not too excited about ventpipes poking out the side of the barn, but this was about as low-profile as I could hope for). The little stove is loaded with pellets, then self-regulates the heat output by controlling the feed rate into the burner. Having insulated the roofs with spray foam, I was excited with the thought of finally working inside a warm, dry environment for the rest of the winter. So far, I love the stove- it burns and burns, requiring very little maintenance or attention. On the downside, the flame is not as "real" as a traditional wood-burning stove. But then, I won't have to spend a couple weeks of my year cutting, splitting, and hauling firewood. Unfortately, after running the little pellet burner all day with no appreciable temperature increase, I realized the laws of thermodynamics are working hard against me. The outside temp has been well below freezing for weeks (many days are below 0F lately), so the barn and its concrete slab floor are likely hanging at around 15 degrees inside. A quick calculation showed that it would take well over 750,000 BTUs of heat to raise the building temp up to 70 degrees, not including the heat loss through the walls (probably another 15,000BTUs/hour right now). The pellet stove kicks out a max of 30,000 BTUs/hour. Do the math- it isn't pretty. Once the building is insulated and heated up to room temp, the stove will be more than adequate to keep it toasty warm on a -40F morning, but right now it is like trying to melt a skating rink with a butane lighter while the A/C in running on high! Not. Gonna. Happen. Guess I'll be working in the cold for another few weeks :(

Saturday, August 25, 2007

Big Timber

Just as we started sheathing the silo, Glen came over with his boom and a trailer FULL of beams for the floor joists of the barn. They were freshly milled and very heavy (300 lbs each, until they dry out), so thankfully he stuck around for a few hours to set them in place with the crane. The 4X10 beams look great, and are about as 'sustainable' as you can get- they were all milled from locally-harvested blowdowns. No trees were killed for this project! Glen also left me with a pile of thick slabs that will be used to make tables, benches, countertops, etc. Okay, back to the silo..

Wednesday, August 08, 2007

Read my mind.

"Stand back ladies, I've got this COMPLETELY under control." or, "Do we really need in-floor heat?" or, "Has anyone seen the other end of this tubing?" or, "This stopped being fun about 4 days ago..." What I was really thinking was, "Good thing I have Lisa and Tammy here to help figure this out!" Thanks to them, we laid down 600 feet of 7/8" PEX tubing throughout the slab in just a few short hours. Sliding it under the pathway form was a little tricky, but it worked out okay. (Photo by Claire Schotzko) I spent the rest of the day zip-tying the PEX to the rebar and making sure everything was kosher since we will be pouring concrete in the morning! I also connected the PEX to the distribution manifold (where all the strands are bunched up in lower right corner) and pressurized the system to 50psi to check for leaks. It held pressure all night, so that was a relief.